작업일보 데이터를 활용한 조적공사 작업간섭 요소 도출
Masonry work interference factor deduction based on daily report data analysis
초록
Construction project involves numerous repetitive operations. Especially in high-rise and apartment houses projects, the amount of repetitive operations increase and a preceding operations delay causes serious damage to the total duration of the project. This study deducts work delay factors by site engineer interview and survey. The study analyzes daily report data to deduct crucial processes affecting masonry work which has been investigated to be one of preliminary processes conducted at the beginning of finish work.
- 제목
- 작업일보 데이터를 활용한 조적공사 작업간섭 요소 도출
- 제목 (타언어)
- Masonry work interference factor deduction based on daily report data analysis
- 저자
- HAN SEUNGWOO
- 학회명
- 한국건축시공학회 2015 추계학술발표대회
- 개최지
- 연세대학교
- 학회 개최일
- 2015-11-14 ~ 2015-11-14